Enterprise IV Corporate Center - Parking Garage

As urban and suburban space becomes more limited, developers may begin looking closer at the type of space solution developed by the Enterprise IV office building and parking structure in Shelton, Connecticut. The project, the first of its kind in the state, used an all-precast concrete design to place a five-story office building on top of a 2-level above-grade parking structure. The design solved the owner's need for additional office space while also providing parking space not only for the new structure but also for adjacent buildings.

The design solved a variety of challenges, explains Robert Scinto, chairman of the developing firm R.D. Scinto Inc. As the company was preparing to construct the last of nine buildings in the Enterprise Corporate Center, Scinto realized that changing demands had left only one space available, which was also required for parking. "We had a tenant that needed about 90,000 square feet, but we could only satisfy that need by building on the site of an existing parking lot. But we still needed to provide parking, not only for the new building but for current tenants, too."

The developer first considered building a precast parking garage with a steel-framed office building above. But before solidifying that plan, Scinto decided to explore the benefits of creating an all-precast structure. He discussed the possibilities with designers at Blakeslee Prestress Inc. in North Branford Connecticut, which had supplied precast concrete components for all of the company's parking structures during the previous 10 years.

Precast Saves Time And Money

The Blakeslee design team told Scinto that while it was feasible to build a steel structure atop a precast parking structure, the developer could realize greater savings in both time and money if both the office building and the parking structure were built from precast concrete. Scinto liked many aspects of the proposal. "I knew that precast minimizes the potential maintenance problems associated with a steel and concrete structure," he says. "Since I retain ownership of the buildings I build, that's particularly important to me."

Prev
1
2
3
4
5
6
 

Project Details

City:

Shelton
 

State:

CT
 

Precaster:

 

Owner:

R.D. Scinto, Shelton, CT
 

Architect:

Kasper Group, Bridgeport, CT
 

General Contractor:

R.D. Scinto Inc., Shelton, CT
 

Engineer:

Kasper Group, Bridgeport, CT
 

Sq. Ft.:

196,700 (Office Building)
173,000 (Parking Garage
 

Floors/Levels:

5-story (Office Building)
4 levels (659 parking spaces)
 

Precast Structural Elements:

1149 total pieces (369,700 sf of precast concrete) including:
• 588 precast concrete Double Tees
• 163 precast concrete Spandrels
• 149 precast concrete Shear/K-walls
• 59 precast concrete Inverted T Beams
• 51 precast concrete Stair/Elevator walls
• 49 precast concrete Columns
• 38 precast concrete Stairs with integrated landings
• 30 precast concrete Wall Columns
• 22 precast concrete Solid Slabs
 

Resources

 
 
Back to